--- In amibroker@xxxx, "Tomasz Janeczko" <amibroker@xxxx> wrote:
> Hi,
>
> Indeed there is one problem with variable-period sum( array,
range ) function:
> it is sensitive to the values stored in range array.
> Therefore additional check for range value being empty is needed
> as shown in the example below:
>
> x = peakbars( close, 10, 1 );
>
> range = IIF( isempty( x ), 0, x ); // this check ensures that range
is NOT empty.
>
> graph0 = sum( v, range );
>
>
> Best regards,
> Tomasz Janeczko
> ===============
> AmiBroker - the comprehensive share manager.
> http://www.amibroker.com
>
>
> ----- Original Message -----
> From: <nkishor@xxxx>
> To: <amibroker@xxxx>
> Sent: Monday, July 23, 2001 9:49 PM
> Subject: [amibroker] AFL question
>
>
> > I am trying to get the total volume from one point
> > to the next.
> > X=peakbars(close,10,1) give me a numberof bars .
> > Then I use TotVol=sum(volume,k) and this does
> > not work - infact it detects a bug!
> >
> > Can soemone please check this out. When I run Exploration,
> > I can see the valuse of X as integers but why doesn't it
> > work in getting me the TotVol? Is there another way I can
> > use to get the total volume in a time period?
> >
> >
> > nand
> >
> >
> >
> >
> >
> > Your use of Yahoo! Groups is subject to
http://docs.yahoo.com/info/terms/
> >
> >
> >
|